Skip to main content
Nuclear Safety Cooperation

R1.05/04 A - Lot 3 - Equipment for Automatic Control and Monitoring for the Grouting Unit of the New Radwaste Treatment Facility at Smolensk NPP

Status
  • Closed
Russia
Benefitting Zone
Eastern Europe / North Asia
€ 1,702,550.00
EU Contribution
Contracted in 2007
TACIS
Programme
Technical Assistance to the Commonwealth of Independent States

Details

Type of activity

On Site Assistance

Nature

Supplies

Contracting authority

Rosenergoatom

Method of Procurement

(FR2007) (Ext. act) Supply - International Open Procedure after publication of a contract notice - Art. 243.1(a) IR

Duration

21/08/2007 - 31/12/2012

Contractor

BALTIJOS INFORMACINES SISTEMOS UAB*

Project / Budget year

TACIS 2004 - Nuclear Safety Action Programme / 2004

Background

Smolensk NPP (SmNPP), located in the Smolensk region of Russia, comprises 3 power units. The site lies 3 km away from the nearby town of Desnogorsk on the bank of an artificial lake situated on the river Desna. Unit 1 was commissioned in 1982, Unit 2 in 1985 and Unit 3 in 1990. All three units have reactors of the RBMK-1000 type and were still in operation at the time of this contract.
The existing radioactive waste treatment facility at Smolensk NPP had several safety deficiencies. The waste was not sorted in line with international practice and it was not leak tight. Thus there was the potential for leakage of radioactive material into the surroundings. The methodologies employed for solid waste reduction and disposal lagged behind those employed in similar facilities in western European nuclear establishments. For these reasons Smolensk NPP had decided to construct a new Radioactive Waste Treatment Facility (RWTF) at the NPP site.

The RWTF is a component of the plant radioactive waste treatment system, used for acceptance, sorting and processing of liquid and solid radioactive waste generated during operation and maintenance as well as during future decommissioning of the reactor units. It is also used for interim storage of processed waste. Radwaste processing is carried out to reduce the volume of waste arisings and condition the waste such that they can be safely stored, transported and disposed of.
The design of the Smolensk NPP RWTF includes the following units:

  • A liquid radwaste (LRW) processing facility (using ion exchange);
  • Two grouting (cementation) lines for liquid radwaste (LRW);
  • A sorting unit;
  • An incinerator for low-level solid and liquid radioactive waste;
  • A 950kN force waste compaction unit for low-level solid radwaste (SRW);
  • A supercompactor unit;
  • A low level metal decontamination facility;
  • A smelter for thermal decontamination and scrap metal processing.

Liquid radwaste may be first processed in the ion exchange units or fed directly to one of the two grouting lines. The output from the ion exchange units (liquid and sludge) is also processed in the grouting lines. In these lines, all types of LRW are processed. These wastes are supplied via an overhead pipe gantry from the LRW storage tanks and other LRW processing installations located in the RWTF. The mixtures are combined with cement in the grouting line. Only decanted still-residue sludge is processed in the LRW line.

Low-level solid radwaste (SRW) is received in the RWTF and sorted in the sorting unit according to whether the material is to be incinerated, compacted or decontaminated. Combustible waste will be directed to the Incinerator. During incineration of the SRW, the volume can be reduced by up to 50 times. Waste is loaded into the furnace via the interlocked gate. Gases generated during this process go to an off-gas treatment system whilst proportioned ash is discharged from the furnace into a drum located in a shielded container fitted with exhaust ventilation. The ash is watered and the drum in the shielded container is transported to the grouting lines when required.
The gases discharged from the incinerator are purified and discharged into a duct. Following purification, the gases are analysed by an Automated Off Gas Analyser System.
Non-combustible wastes are loaded, after additional check sorting, into a 200 l drum. Dependent upon the decision of the operator, a drum containing SRW may then be either:

  • Compacted, in-drum, in the 950kN press and sent directly into the storage system
  • supercompacted (15 000 kN minimum) and sent into the storage system
  • compacted and then supercompacted and sent into the storage system

For waste compacted 'in-drum', after several cycles of “filling – compaction” (3-4 times) the drum is capped and transported to a weight measurement unit and radiometric analysis unit. Following radiometric assaying, the drum is transported from the RWTF for storage or supercompaction.
Waste volumes can be reduced to 3-5 times by in-drum compaction, using a 950KN compactor. A further reduction will be achieved by supercompaction of the drums. Several supercompacted drums can be further enclosed in concrete overpack containers.
In the framework of the TACIS 2004 Nuclear Safety Programme, the Rosenergoatom/Smolensk NPP agreed with the European Commission a project to improve the nuclear safety associated with the treatment of radioactive waste arising at the site through the supply of equipment for the intended new RWTF.
The general purpose of the intended TACIS equipment supply projects was to:

  • Eliminate the deviations from the State safety regulations and rules.
  • Allow the operation of the new Radwaste Facility to be on a level comparable with similar western European Radwaste facilities
  • Permit the use of equipment and monitoring systems, which were not available in Russia at that time.
  • Enable the application of state-of-the-art testing methods and thus the exclusion of potentially dangerous and inaccurate testing methods.

The subject of the TACIS equipment supply contracts was the design, manufacture, delivery, including any documentation required, certification, acceptance tests, supervision of the installation and supervision of commissioning, support to licensing, after-sales services (maintenance support) and training by the Contractor of the following goods:
LOT 1 (Contract 99577): Supply of a Supercompactor and Associated Equipment
Lot 1 was to provide the Supercompactor and Ancillary Equipment. The equipment was intended to facilitate reduction of solid radioactive waste volumes by supercompaction, giving increased safety during storage, transportation and disposal.
LOT 2 (Contract 140193): Monitoring and Analysis Equipment
Lot 2 was the provision of three distinct sets of equipment for the Radwaste Treatment Facility (RWTF):

  • Fixed Segmented Gamma Spectrometers and associated drum handling equipment. These were to be installed in each grouting line of the RWTF and used to conduct radiological assays of drums after being filled with radwaste.
  • Miscellaneous equipment for the Radiochemical Laboratory of the (RWTF). This equipment was intended for off-line monitoring of the processes involved in radwaste treatment by carrying out chemical, physical-chemical and radionuclide analyses.
  • An Automated Incinerator Off-Gas Analyser System. This equipment was for continuous automated gas-analysis of the incinerator exhaust gases.

LOT 3 (Contract 140194): Automatic Control and Monitoring for the Grouting Lines
Lot 3 was the provision of an Automatic Control and Monitoring System for the grouting lines of the RWTF. This equipment was intended for high level surveillance, monitoring and on-line control of the process parameters of the grouting lines in the Central Control Room of the RWTF.
LOT 4 (Contract 140196): Process Control Equipment for the Grouting Lines
Lot 4 was to provide three separate devices to be installed, along with equipment provided under SmNPP responsibility, in the grouting lines of the RWTF. The Process Control Equipment (PCE) was intended to provide Smolensk NPP with enhanced control facilities for the quality control of the Grouting Lines process in three distinct operations:

  • A proportioning mechanism for the dry cement/bentonite that is used to combine with the pulp/LRW into a concrete mix,
  • A two-phase level monitoring of the pulp/liquid radwaste inlet tank, and
  • A flow control (or proportioning) of the pulp LRW flow from this tank.

The result will be enhanced quality of the resulting concrete mix.

Objectives

This contract was for Lot 3: Supply of Automatic Control and Monitoring System for the Grouting Lines.
The Radwaste Treatment Facility includes two grouting lines for processing still residue, ion exchange resins, perlite, ash and sludge and has a capacity of 2.5 drums per hour per grouting line. The Liquid Radwaste (LRW) cementation process of each of the two grouting lines comprises the following operations:

  • still reside (SR) intake and concentration;
  • pulp intake and decantation (pulp separation);
  • pulp and SR concentrate mixing to the defined mass ratio of solid/liquid;
  • preparation and delivery of cement and admixtures blend;
  • proportioned supply of LRW into the mixer;
  • proportioned supply of cement and admixtures blend into the mixer;
  • mixing of LRW with cement and admixtures blend;
  • packaging of cement compound into drums;
  • compound hardening;
  • drum outer surface decontamination;
  • drum activity monitoring and certification (monitoring of the equivalent dose rate, specific activity, cement compound radionuclide composition and logging of the package weight).

The grouting lines also perform conditioning and cementation of ash residue from the incinerator.
The Automatic Control and Monitoring System (ACMS) is intended for process monitoring and on-line control of the equipment of the grouting lines. The purpose of the ACMS is to ensure reliable operation of the grouting lines by implementation of adequate monitoring and control of the process.
The ACMS comprises a complete set of input/output channels located in the Control Room of the RWTF. The input channels receive information from the plant. Inbuilt algorithms determine the information which is sent to the plant to provide adequate control of the plant systems and provide information to the operator. Operator workstations display the information to the operator. The displays are hierarchal, allowing overview of the total plant process as well as detailed display of areas of interest to the operators. Warning and alarm systems are included. The scope of supply also included an engineering workstation, which is used by the plant specialists to carry out maintenance, investigations and modifications to the software and input/output channels.

Results

The contract was signed in August 2007. The Factory Acceptance Tests were performed satisfactorily in November 2009. The equipment was delivered to Smolensk NPP in April 2010 and customs clearance was completed in June 2010. Site Acceptance Testing and commissioning of the equipment associated with grouting line 1 was completed in November 2012 followed by signature of a partial Provisional Acceptance Certificate. Site Acceptance Testing and commissioning of the equipment associated with grouting line 2 was completed in December 2012 followed by signature of the second partial Provisional Acceptance Certificate.