Skip to main content
Nuclear Safety Cooperation

BilibinoNPP-Ev.Tend.R1.08/95 - R1.02/97

Status
  • Closed
Russia
Benefitting Zone
Eastern Europe / North Asia
€ 173,034.00
EU Contribution
Contracted in 2000
TACIS
Programme
Technical Assistance to the Commonwealth of Independent States

Details

Type of activity

On Site Assistance

Nature

Services

Contracting authority

European Commission

Method of Procurement

Direct Agreement & AV DA

Duration

02/05/2000 - 02/11/2005

Partner

Rosenergoatom

Contractor

SOCIETA' GESTIONE IMPIANTI NUCLEARIPER AZIONI

Project / Budget year

WW9817 Nuclear Safety 1998 / 1998

Summary

Bilibino NPP

Bilibino nuclear power and district heating plant (NPDHP) was the first nuclear power station built beyond the Polar Circle in the central part of the Chukotka peninsula, and it provides electricity for the regional mining and gold mining industries.

Four EGP-6 (water-cooled graphite-moderated pressure tube) reactors, with a 48 MW installed capacity, are in operation.

The station works in the load-following mode in the regional energy grid. The station also provides heat and hot running water for the nearby small town and a hothouse complex.

At the time of the initiation of this project the population of the nearby town was 10,000 people - mostly station personnel, geologists, construction workers and gold miners.

Bilibino NPP was connected through two 110 kV lines: the first one, 300 kms long, to Zeliony Mys power plant (2 x 10 MW Gas Turbine) and the second one, 400 kms long, to Pevec where an old small thermal plant was still working. No other electric lines or plants were in the area and no future development or renovation was planned.

For this reason Bilibino NPP often worked in island mode because it was the only reliable power source in this wild and remote region, where, during the winter, temperatures as low as minus 50 °C are normally reached.

Events or accidents that would not have severe consequences or could be easily mitigated in other regions, in Bilibino could degenerate due to the difficulty, and sometimes the impossibility, to transport help during the winter months when the worst climate conditions would exist.

Background

In the framework of the Tacis 1995 programme, it was decided to initiate a project for the re-design and reconstruction of the Emergency Power Supply System of Bilibino NPP. The initial stages of the project preparation were included as part of a large contract between the EC and the Twinning Programme Engineering Group (TPEG) consortium (see contract 23631). TPEG assigned the task to ENEL.

ENEL immediately began an analysis of the emergency systems, based on probabilistic models, which led to some indications on Emergency Power Supply System components' implementation or replacement.

A visit to Bilibino NPP, which was originally foreseen at the end of 1996 and postponed for bad weather conditions in Chukotka, was performed by the ENEL experts in the period from the July 30 to August 5, 1997.

The visit, in addition to the visual inspection of the overall system to evaluate the status, the working conditions, the location of the existing components and to obtaining relevant information from the system operators, had the purpose of defining an agreed set of components to be implemented or replaced either in the framework of the TACIS 95 or in the framework of the TACIS 97 Programme.

Four Specific Projects were identified and in detail:

  • TACIS 95 Programme (see project R1.08/95)
  • Replacement of Emergency D/G Switchboards
  • Replacement of Emergency Circuit Breakers
  • Replacement of Telephone Exchange System
  • TACIS 97 Programme (project R1.02/97D, which was cancelled and reprogrammed in the TACIS 2003 programme - see R1.08/03A)

Substitution of 2,5 MW Gas Turbine with 2x1,25 MW Diesel generators
ENEL prepared, among other documents, a report on the redesign of the Electrical Power Supply System a well as four purchase Technical Specifications for each of the above mentioned replacement projects.

The activities were halted when the contract with TPEG ended and the continuation was the purpose of the present service contract awarded to ENEL (later Sogin) on May 2, 2000.

Objectives

The objective of the project was to finalise the tender documentation that was almost completed under the contract with TPEG and to proceed with the equipment through the following activities:

R1.08/95:

  • Evaluation of tenders for the procurement of:
    • Emergency D/G Switchboards
    • Emergency Circuit Breakers
    • Telephone Exchange System

Supervision of the installation of the above equipment at Bilibino NPP
R1.02/97D:

  • Preparation of the tender evaluation criteria for the purchasing of the 2 diesel generators (DGs)
  • Evaluation of tenders for the procurement of the DGs
  • Supervision of the installation of the DGs at the Bilibino NPP site.

The supervision activities were envisaged to take place during the same summer period in order to save resources and maximise the value of the supplied components.

Results

The contract was signed in May 2000 and was concluded in November 2005.

The tender procedure for R1.08/95 resulted in the contracting of the Emergency D/G Switchboards and the Emergency Circuit Breakers with the company Schneider (see project R1.08/95). No compliant offers were received for the Telephone Exchange System and it was decided not to retender for this equipment.

The tender procedure for R1.02/97D was unsuccessful due to the one tender received not being technically compliant with the tender technical requirements. The EC decided to revise the Technical Specifications and re-launch the call for tender.

This resulted in additional activities for the Consultant. Moreover, the delays introduced by the retendering meant that the on-site supervision activities for the installation of the diesel generators could now no longer be performed in the same summer period as those for project R1.08/95. There was insufficient budget in the present contract to cover these additional activities so a separate contract was placed with Sogin for the retendering and on-site installation supervision activities.

The Emergency D/G Switchboards and Emergency Circuit Breakers were successfully delivered and installed at the NPP.