- Status
- Closed
Details
- Type of activity
Equipment Supply
- Nature
Supplies
- Contracting authority
Armenian NPP
- Method of Procurement
(FR2007) Negotiated Procedure - External Actions
- Duration
22/12/2003 - 22/04/2005
- Partner
Armenian NPP
- Contractor
MIRION TECHNOLOGIES (CANBERRA BNLS)
- Project / Budget year
ZZ0003 Nuclear Safety 2000 / 2000
Background
This project aimed at replacing the obsolete radiological Instrumentation and increase capability of the plant radiation monitoring system.
Results
A progress meeting was held on-site on October 7th, 2004 and a final schedule with a new delivery time of 16 months (April 2005) was agreed upon. Addendum 1 to Contract n. 2003/072-768, including new delivery deadline, was endorsed by EC on February 17th, 2005.
Factory acceptance tests were successfully performed in June 2005 and equipment was delivered on-site. Installation activities were completed during the 2005 outage.